Problem
Create the network diagrams and bar charts for the given Activity Tables (without lags and with lags
a) Determine Forward Pass Early Start and Early Finish for both.
b) Determine Backward Pass Late Start and Late Finish for both.
c) Determine Floats both.
d) Determine critical Paths for both.
e) How long will the project take to finish for both?