Discuss the below in detail:
Q: The Shady Farm Milk Company can process milk at a fixed rale of 6,000 gallons' hour. the company's clients request 100,000 gallons of milk over the course of one day. This demand is spread out uniformly from 8 a.m. middot 6 p.m. the company starts producing at 8 a.m. and continues to work until all of the demand has been satisfied. How long does a client requesting milk at 6 p.m. have to wait to have his demand satisfied?