Problem: A project is planned for twelve months at the total cost of $120,000, which will be spent equally over the periods. It is now month 4 and your project's CPI is .9091 and its SV is $10,000. How is the project performing? 1) Over budget and behind schedule 2) Under budget and ahead of schedule 3) Over budget and ahead of schedule 4) Under budget and behind schedule