How does earned value give a clearer picture of the project


Instructions:

Please answer the following questions. Your responses should be between 100 and 150 words, double-spaced, and follow the American Psychological Association (APA) Publication Manual, 6th Edition.

Questions:

1. How does a Tracking Gantt chart help communicate project progress?

2. How does earned value give a clearer picture of the project schedule and cost status than a simple plan versus actual system?

3. Schedule variance (SV) is in dollars and does not directly represent time. Why is it still useful?

4. How would a project manager use the CPI?

5. What are the differences between BAC and EAC?

Request for Solution File

Ask an Expert for Answer!!
Finance Basics: How does earned value give a clearer picture of the project
Reference No:- TGS01004035

Expected delivery within 24 Hours