High-low technique of analyzing costs


Task1. Herbart Company collected the following information on power costs and factory machine usage for the last six months:

 

Power Cost

Factory Machine Hours

January

$24,400

13,900

February

30,300

17,600

March

29,000

16,800

April

22,340

13,200

May

19,900

11,600

June

14,900

6,600

 
Required: Using the high-low technique of analyzing costs answer the following questions and demonstrate all calculation to support your answers.

Part (a) What is estimated variable portion of power costs per factory machine hour?

Part (b) What is estimated fixed power cost each month?

Part (c) If it is estimated that 10,000 factory machine hours will be run in the month of July, what is the anticipated total power cost for July?