Hart manufacturing operates an automated steel fabrication


Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 45% of the total throughput (manufacturing cycle) time is spent on non-value-added activities. Delivery cycle time is 12 hours, waiting time during the production process is 3 hours, queue time prior to starting the production process is 2 hours, and inspection time is 1.2 hours.

a. What is the throughput (manufacturing cycle) time for the operation?

b. What is the move time recorded for the operation?