Harry's Picture manufactures diverse picture frames. He spends $ 20 on raw material for each frame. Every new employee takes 5 hours to make the first picture frame and 4 hours to make the second. He pays $ 20 per hour to his worker. The manufacturing overhead charge per hour is $ 10.
Evaluate what is the total cost of building 8 picture frames by a new employee using the cumulative average-time method?