Hagar Industrial Systems Company (HISC) is trying to decide between two different conveyor belt systems. System A costs $200,000, has a four-year life, and requires $65,000 in pretax annual operating costs. System B costs $282,000, has a six-year life, and requires $59,000 in pretax annual operating costs. Both systems are to be depreciated straight-line to zero over their lives and will have zero salvage value. HISC always needs a conveyor belt system; when one wears out, it must be replaced. Assume the tax rate is 30 percent and the discount rate is 9 percent. What is the EAC for each project using aftertax cash flows?