Given the network plan that follows, compute the early, late, and slack times. What is the project duration? using any appraoch you wish ( e.g., trial and error), develop a loading chart for resourses, Electrical Engineers (EE), and resource, Mechanical Engineers (ME). Assume only one of each resource exsists. Given your resource schedule, compute the early, ;ate, and slack times for your project. Which activities are now critical? What is the project duration now? Could something like this happen in real projects?