Given the information below:
1. Construct a network using the AON (Activity on Network method) like we did in class. See problem 3.4 on page 90 and its answer in the Appendix on page A8.
2. Show how you calculate the path in weeks for each of the three paths.
3. Which path is the critical path?
Immediate Time
Activity Predecessor (weeks)
A --- 1
B --- 4
C A 1
D B 2
E B 5
F C, D 7
G E 2
H F, G 3