Given the following task times and sequence develop a


Given the following task, times, and sequence, develop a balanced line capable of operating with a 10-minute cycle time at Dave Visser’s company. Task Time Element Task Time Element Element (minutes) Predecessor Element (minutes) Predecessor A 3 — E 3 C B 5 A F 3 B, D C 7 B G 5 D D 5 — H 6 G a) Draw the precedence diagram. b) Assign tasks to the minimum feasible number of work stations according to the greatest time remaining (ranked positional weight) decision rule. c) What is the efficiency of the process?