Given the following information with demand and performance cycle certainty:
Average daily demand = 40 units
Performance cycle = 10 days
Order quantity (from (EOQ) = 400 units
Review period = 2 weeks (10 working days)
Calculate:
a) the reorder point utilizing the perpetual review method
b) the reorder point utilizing the periodic review method