Given the following information calculate the cv sv cpi and


Given the following information, calculate the CV, SV, CPI, and SPI for this project. Also provide recommendations to improve the project's performance if needed.

Activity A: This activity is 75% complete with an original budget of $200,000. Costs to date are $65,000, and the project is at the beginning of Week 3 of 4.

Activity B: This activity is complete. It was completed 3 weeks late, and it was supposed to be completed in 6 weeks. It was to have cost $500,000. Its true costs were $550,000.

Activity C: This activity starts next week. It is planned to cost $400,000 and take 6 weeks.

Activity D: This activity is 40% complete, at a cost of $80,000. It is at the end of Week 5 of 8 and was projected to cost $200,000.