Given the follow bill of materials tree and other data


Question # 1

Given the follow bill of materials tree and other data, construct the MRP records for parts A, B and C given the master production schedule below. In considering safety stocks, we require that on hand inventory never drop below the specified safety stock level. The demand provided in the table below is for Part A.

Week

1

2

3

4

5

6

Demand

5

15

18

8

12

22

1309_111.png

This table contains some extra information that needs to be factored into your MRP schedule!!!!!!

Part

Lead time

Safety Stock

Order Quantity

On hand Inventory

Expected Receipts

A

1

0

20

21

0

B

2

0

40

20

32 units, period 1

C

1

10

Lot for Lot

50

0

 

Request for Solution File

Ask an Expert for Answer!!
Operation Research: Given the follow bill of materials tree and other data
Reference No:- TGS01274209