Antonio White's machine shop uses 3,500 brackets during the course of a year. These brackets are purchased from a supplier 80 miles away. The following information is known about the brackets:
Annual demand:
|
3,500
|
Holding cost per bracket per year:
|
$1.45
|
Order cost per order:
|
$15.50
|
Lead time:
|
2 days
|
Working days per year
|
260
|
- Given the above information, what would be the economic order quantity (EOQ)?
- Given the EOQ, what would be the average inventory? What would be the annual inventory holding cost?
- Given the EOQ, how many orders would be made each year? What would be the annual order cost?
- Given the EOQ, what is the total annual cost of managing the inventory?
- What is the time between orders?
- What is the reorder point (ROP)?