Given is a CPM project network diagram as shown below.

The Project Completion time = ______________ days.
The Earliest Start time, ES, of Activity G = ______________ days.
The Latest Finish time, LF, of Activity C = _____________ days.
The critical activities are = _________________ (ex. Fill in answer as: ABCD)