Given EVM data, estimate the cost at completion of a project using the method "EAC based on Combined Cost and Schedule Performance." Reference Figure 11-3. (Answers are approximate) BCWS = $82.2M BCWP = $70.5M ACWP = $95.5M BAC = $105.5M Assume PMB validity is maintained
$150M
$160M
$170M
$130M
Use Excel spreadsheet with this problem with sums embedded.