Given a total labor cost of $320,000, a Fringe Benefits rate of 43%, an Overhead Rate of 62%, a General & Administrative rate of 12%, Other Direct Costs of $27,000, and a desired Fee of 9%:
What is the Cost Factor?
What is the Price Factor?
What should the total bid price be?