Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted.

The activities, immediate predecessors, and times appear in the accompanying table:

Activity

Immediate? Predecessor(s)

Time? (days)

A

-

2

B

-

7

C

-

2

D

B

10

E

?A, D

5

F

C

5

G

?E, F

8

This exercise contains only parts? b, c, and d.

b) The critical activities for the leadership training program development project are

B - D - E - G

c) The project length for the leadership training program development project? = ?? days.

What are the slack times for each activity

 