Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted.
The activities, immediate predecessors, and times appear in the accompanying table:
Activity
|
Immediate? Predecessor(s)
|
Time? (days)
|
A
|
-
|
2
|
B
|
-
|
7
|
C
|
-
|
2
|
D
|
B
|
10
|
E
|
?A, D
|
5
|
F
|
C
|
5
|
G
|
?E, F
|
8
|
This exercise contains only parts? b, c, and d.
b) The critical activities for the leadership training program development project are
B - D - E - G
c) The project length for the leadership training program development project? = ?? days.
What are the slack times for each activity