Problem: General Foundry’s project crashing data are shown below. Crash this project using CPM. What are the final times for each activity after crashing?
|
Time (Weeks) |
Cost |
|
|
Activity |
Normal |
Crash |
Normal |
Crash |
Crash Cost P/Week |
Critical Path |
A |
2 |
1 |
$ 22,000.00 |
$ 23,000.00 |
$ 1,000.00 |
Yes |
B |
3 |
1 |
$ 30,000.00 |
$ 34,000.00 |
$ 2,000.00 |
No |
C |
2 |
1 |
$ 26,000.00 |
$ 27,000.00 |
$ 1,000.00 |
Yes |
D |
4 |
3 |
$ 48,000.00 |
$ 49,000.00 |
$ 1,000.00 |
No |
E |
4 |
2 |
$ 56,000.00 |
$ 58,000.00 |
$ 1,000.00 |
Yes |
F |
3 |
2 |
$ 30,000.00 |
$ 30,500.00 |
$ 500.00 |
No |
G |
5 |
2 |
$ 80,000.00 |
$ 86,000.00 |
$ 2,000.00 |
Yes |
H |
2 |
1 |
$ 16,000.00 |
$ 19,000.00 |
$ 3,000.00 |
Yes |