Solve the below:
Q: The manager of a Burger Doodle franchise wants to determine how many sausage biscuits require the following resources:
Biscuit Labor(hr.) Sausage(lb.) Ham(lb.) Flour(lb.)
Sausage 0.010 0.010 - 0.04
Ham 0.024 - 0.15 0.04
The franchise has 6 hours of labor available each morning. The manager has a contract with a local grocer for 30 pounds of sausage and 30 pounds of ham each morning. The manager also purchases 16 pounds of flour. The profit for a sausage biscuit is $0.60; the profit for a ham biscuit is $0.50. The manager wants to know the number of each type of biscuit to prepare each morning in order to maximize profit.
Formulate a linear programming model for this problem.