Tej Dhakar’s company wants to establish kanbans to feed a newly established work cell. The following data have been provided. How many kanbans are needed?

Daily demand    1,000 connectors
Lead time    2 days
Safety stock    day
Kanban size    500 connectors

Provide complete and step by step solution for the question and show calculations and use formulas.