Problem: A company is evaluating two options for expansion by making calculators.
Plan A: expansion basss on ordinary production equipt at cost of 6 million, and production will cost $25 per unit
Plan B; expansion based on more modern equipt and will cost $10 million, production per unit will be $20
For what ranges of demand quantity in each option is better?