Activity Crashing
Problem Statement
For the network above, assume that an activity's daily expedite-cost in dollars per day is equal to the activity's time (e.g., the cost to reduce the activity time of H by one day is $6). Further, assume that each activity may be crashed only 1 day. What activities should be crashed to reduce the project duration by 3 days at least cost?