For activities on a traditional project’s critical path
a) Earliest start time (ES) equals latest start time (LS)
b) Earliest start time (ES) is greater than latest start time (LS)
c) Earliest start time (ES) is less than latest start time (LS)
d) Earliest start time (ES) equals latest finish time (LF)