1) Following are elements of a WBS for a project to build a bunk bed. Using the information supplied here, create a WBS and carry out a bottom-up cost estimate.
2) Following is a listing of items to be considered in costing a PC game development project. Use this data to develop a parametric estimate of the cost of the project.
3) For the table below
a. Create a PERT/CPM chart
b. Identify the critical path and compute project duration
c. Compute Latest Start, Earliest Start, and Float (Slack)