Following are cost and schedule data for a project that is


Following are cost and schedule data for a project that is underway.

Using the cost data in the cost table above, create a cumulative cost curve comparing actual versus planned costs

Using the schedule data in the schedule table above, create a Gantt chart comparing actual versus planned schedule performance

Summarize in words what you see project status to be at this time. What do you predict regarding the final cost and final schedule for the project?

Request for Solution File

Ask an Expert for Answer!!
Operation Management: Following are cost and schedule data for a project that is
Reference No:- TGS01266168

Expected delivery within 24 Hours