An organization planned to use $82 of material per unit of output, but it actually used $80 per unit. During this period, the company planned to make 1,200 units, but actually produced only 1,000 units. The flexible budget amount for materials is:
a) $80,000.
b) $82,000.
c) $96,000.
d) $98,400.