Fletcher Company collected the following data regarding production of one of its products. Compute the direct materials price variance.
Direct materials standard (6 lbs. @ $2/lb.)
|
$12 per finished unit
|
Actual direct materials used
|
243,000 lbs.
|
Actual finished units produced
|
40,000 units
|
Actual cost of direct materials used
|
$483,570
|