Question: Five jobs must be scheduled for batch processing on a mainframe computer system. The processing times and the promised times for each of the jobs are listed here.
Assume that the current time is 10:00 A.M.
a. If the jobs are scheduled according to SPT, find the tardiness of each job and the mean tardiness of all jobs.
b. Repeat the calculation in part (a) for EDD scheduling.