First printing and copy center has 4 more jobs to be


First Printing and Copy Center has 4 more jobs to be scheduled, in addition to those shown in Example. Production scheduling personnel are reviewing the Gantt chart at the end of day 4.

• Job D was scheduled to begin early on day 2 and to end on the middle of day 9. As of now (the review point after day 4), it is 2 days ahead of schedule.

• Job E should begin on day 1 and end on day 3. It is on time.

• Job F was to begin on day 3, but maintenance forced a delay of 1½ days. The job should now take 5 full days. It is now on schedule.

• Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to complete.

• Develop a Gantt schedule chart for First Printing and Copy Center.

Example
GANTT SCHEDULING CHART First Printing in Winter Park, Florida, wants to use a Gantt chart to show the scheduling of three orders, jobs A, B, and C.