First printing and copy center has 4 more jobs to be


First Printing and Copy Center has 4 more jobs to be scheduled, in addition to those shown in Example 3 in the chapter. Production scheduling personnel are reviewing the Gantt chart at the end of day 4.

  • Job D was scheduled to begin early on day 2 and to end on the middle of day 9. As of now (the review point after day a), it is 2 days ahead of schedule,
  • Job E should begin on day I and end on day 3. It was on time.
  • Job F was to begin on day 3, but maintenance forced a delay of 1B days. The job should now take 5 full days. It is now on schedule.
  • Job G is a day behind schedule. It started at the beginning of day 2 and should require 6 days to complete. Develop a Gantt schedule chart for First Printing and Copy Center.