Given:
Budgeted production 5,100 drills
Standard machine-hours per drill 10.4 machine-hours
Standard indirect labor $10.20 per machine-hour
Standard power $3.80 per machine-hour
Actual production 5,300 drills
Actual machine-hours 36,750 machine-hours
Actual indirect labor $378,595
Actual power $137,200
What is the variable overhead rate variances for indirect labor and for power?