Discuss the below:
Q: The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4, 800 units per 40-hour workweek:
Task Performance time(sec) Predecessors
A 24 -
B 27 A
C 12 A
D 15 A
E 10 B,C
F 18 D,E
a) Given the demand, the cycle time for the production of the new train set = 30 seconds (round your response to one decimal place)
b) The theoretical minimum number of workstations = 4 (round your response up to the next whole number)
C) Using the longest operation time rule, the assignment of tasks to workstations should be: