Balance the assembly line for the tasks contained in the table. The desired output is 240 units per day. Available production time per day is 480 minutes.
Work Element
|
Time (Sec.)
|
Immediate Predecessor(s)
|
A
|
40
|
---
|
B
|
45
|
---
|
C
|
55
|
A
|
D
|
55
|
B
|
E
|
65
|
B
|
F
|
40
|
C,D
|
G
|
25
|
D,E
|
a) What is the desired Cycle time in seconds?
b) What is the theoretical minimum number of stations?
c) Use trial and error to work out a solution in the table below. Your efficiency should be at least 90%. (10 Points)