Shirley Hopkins is developing a program in leadership training for middle managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table.

Activity Immediate Predecessor Time (Days)
A - 2
B - 5
C - 1
D B 10
E A,D 3
F C 6
G E,F 8

a. Develop an AON network for this problem.
b. What is the critical path?
c. What is the total project completion time?
d. What is the slack time for each individual activity?