Find the schedule and cost variances for a project that has


1. Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. Show work and provide a detailed explanation of the results.

2. Given an activity in an advertising project whose planned cost was $12,000 but actual cost to date is $10,000 so far and the value completed is only 70 percent, calculate the cost and schedule variances. Will the client be pleased or angry? Show work and provide a detailed explanation of the results.