Project Management Assignment
If your last name begins A through L, address the following question. Be sure to show ALL calculations and explain what your answers tell you.
You have just taken over a project from another project manager. Incomplete information is available to you on the project status. You have been told that the cost performance index (CPI) = .92, the earned value (EV) = $322,000 and the planned value (PV) = $180,000. What is the actual cost (AC) for the project? What's the schedule variance (SV) for the project? What about the SPI and the CSI?
If your last name begins M through Z, address the following question. Be sure to show ALL calculations and explain what your answers tell you.
Activity A is worth $200, is 100% complete, and actually cost $200. Activity B is worth $75, is 90% complete, and actually cost $120 so far. Activity C is worth $200, is 75% complete and has cost $175 so far. The total budget is $1000. Find the project's: ETC, VAC, CPI, CV, PV, and EAC.
Format your assignment according to the following formatting requirements:
1. The answer should be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.
2. The response also includes a cover page containing the title of the assignment, the student's name, the course title, and the date. The cover page is not included in the required page length.
3. Also include a reference page. The Citations and references should follow APA format. The reference page is not included in the required page length.