Find the optimal unit commitment schedule for the units to


You are given three generating units and asked to find the optimal unit commitment schedule for the units to supply load over a 4-h time period.

Hour

MW load

1

400

2

1000

3

1600

4

400

Gen 1:F1(P1) = 2200 + 25P1 + 0.025*P12 where 220<=P1<=600 MW

Gen 2:F2(P2) = 1500 + 11P2 + 0.02*P22 where 350<=P2<=800 MW

Gen 3:F3(P3) = 1000 + 20P3 + 0.015*P32 where 150<=P3<=600

Each generator has a start-up cost that must be factored in when the unit starts. You should assume that this start-up cost is incurred even if the unit was on then off for only one or two hours and then gets turned back on.

Generating Unit

Start-Up cost

1

2400

2

3000

3

3400

Find the optimal unit commitment schedule.

Request for Solution File

Ask an Expert for Answer!!
Dissertation: Find the optimal unit commitment schedule for the units to
Reference No:- TGS01729055

Expected delivery within 24 Hours