Find the normal time for this operation - compute the


Susan Cottenden clocked the observed time for welding a part onto truck doors at 5.3 minutes. The performance rating of the worker timed was estimated at 105%.

Find the normal time for this operation.

Note: According to the local union contract, each welder is allowed 3 minutes of personal time per hour and 2 minutes of fatigue time per hour. Further, there should be an average delay allowance of 1 minute per hour.

Compute the allowance factor and then find the standard time for the welding activity.

Request for Solution File

Ask an Expert for Answer!!
Project Management: Find the normal time for this operation - compute the
Reference No:- TGS01659060

Expected delivery within 24 Hours