Suppose that an investment project has an immediate cost of $100 million followed by costs of $50 million at the end of one year and a further $25 million at the end of two years. Net revenues (i.e., revenues in excess of operating costs) accrue in the amount of $16 million at the end of each year beginning in three years' time. Find the net present value of this investment project given an interest rate of 9%.