Find the minimum number of service needs for production


Under ideal conditions, a service bay at a Fast Lube can serve 6 cars per hour. The effective capacity and efficiency of a fast Lube is service bay are known to be 5.5 and 0.880 respectfully. What is the minimum number of service bays Fast Lube needs to achieve an anticipated production of 200 cars per 8-hour day?