Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows:
Direct material of 4.50 yards at $5.40 per yard
Direct labor of 2.50 hours at $19.00 per hour
Overhead applied per sleeping bag at $17.00
- In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.90 per yard. The labor used was 11,700 hours at an average rate of $17.50 per hour. The actual overhead spending was $96,200.
Problem 1: Determine the labor rate variance and round to the nearest whole dollar.