Find the labor rate variance for bowie sporting goods


Bowie Sporting Goods manufactures sleeping bags. The manufacturing standards per sleeping bag, based on 5,000 sleeping bags per month, are as follows:

Direct material of 4.50 yards at $5.40 per yard
Direct labor of 2.50 hours at $19.00 per hour
Overhead applied per sleeping bag at $17.00

  • In the month of April, the company actually produced 5,200 sleeping bags using 27,300 yards of material at a cost of $5.90 per yard. The labor used was 11,700 hours at an average rate of $17.50 per hour. The actual overhead spending was $96,200.

Problem 1: Determine the labor rate variance and round to the nearest whole dollar.