Consider a waiting line system with the following parameters: number of servers = 3 customer arrival rate = 5 per minute customer service rate (per server) = 2 per minute coefficient of variation of interarrival times = 0.8 coefficient of variation of service times = 0.6 Find the expected length of the waiting line.