Find the earliest expected completion date of the project


Task: Critical Path

The following table provides the optimistic, most likely and pessimistic times for a project which has five activities. Use this information to solve the followings questions.

Activity    Optimistic    Most Likely  Pessimistic    Precedent

A           3           4           5           --

B           5           8           12          A

C           8           9           10          A

D           1           2           3           B,C

E           3           4           5           D

a. Find the earliest expected completion date of the project

b. Find variance for activity C

c. Find the variance of critical path

d. Find early finish time for activity C