Problem: Can you help me get started with this assignment?
Find the Discounted Pay back Periods using Excel:
Project A: -$283,000; $46,000; $89,000; $104,000; $123,000; $187,000; $72,000
Project B: -$318,000; $72,000; $213,000; $131,000; $112,000; $92,000; $64,000
(The interest rate =10%, and the cost recovery policy is 3 years.