--%>

Find the critical ratio of the project using earned value


Problem:

The following project is at the end of its sixth week. Find the cost and schedule variances using the proportional earned value rule. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.

Complete in MS Word or excel.

Activity Predecessors Duration (Wks) Budget $ Actual Costs $ % Complete
a
2 300 400 100
b
3 200 180 100
c a 2 250 300 100
d a 5 600 400 20
e b,c 4 400 200 20

Solution Preview :

Prepared by a verified Expert
Project Management: Find the critical ratio of the project using earned value
Reference No:- TGS01955866

Now Priced at $25 (50% Discount)

Recommended (94%)

Rated (4.6/5)