Q1. Find the critical path and calculate the slack time for the following network

Q 2. A project has the following characteristics
Activity
|
Most optimistic time
(a)
|
Most pessimistic time (b)
|
Most likely time
(m)
|
(1 - 2)
(2 - 3)
(2 - 4)
(3 - 5)
(4 - 5)
(4 - 6)
(5 - 7)
(6 - 7)
(7 - 8)
(7 - 9)
(8 - 10)
(9 - 10)
|
1
1
1
3
2
3
4
6
2
5
1
3
|
5
3
5
5
4
7
6
8
6
8
3
7
|
1.5
2
3
4
3
5
5
7
4
6
2
5
|
Construct a PERT network. Find the critical path and variance for each event.
Q3. Define Simulation and Monte Carlo Simulation. Write its steps also.