Problem: The following project is at the end of its sixth week. Find the cost and schedule variances using the proportional earned value rule. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the ETC and EAC for the project.
Complete in MS Word or excel.
Activity |
Predecessors |
Duration (Wks) |
Budget $ |
Actual Costs $ |
% Complete |
a |
|
2 |
300 |
400 |
100 |
b |
|
3 |
200 |
180 |
100 |
c |
a |
2 |
250 |
300 |
100 |
d |
a |
5 |
600 |
400 |
20 |
e |
b,c |
4 |
400 |
200 |
20 |