Find the average time per unit required to produce the


Find the average time per unit required to produce the first 30 units, if the slope parameter of the learning rate is 92% and the first unit takes 460 hours.

(a) −3.30693E-11 (b) 305.5404 (c) 245 (d) 347.3211